Here are the official summaries from the 2nd and 3rd "public" meetings on adaptive reuse of Charity Hospital, held this spring:
March 16, 2011
March 30, 2011
As I said some time ago, nobody attended because nobody knew about the meetings - and neither the state nor its contractor emailed notice to consulting parties (the method by which the first public meeting was announced) despite having all the email addresses.
Showing posts with label public input. Show all posts
Showing posts with label public input. Show all posts
Wednesday, August 31, 2011
Thursday, May 5, 2011
State of Louisiana, Jacobs Engineering tried to evade programmatic agreement, avoid public input on Charity Hospital adaptive reuse
On October 18, 2010, the State of Louisiana, using Jacobs Engineering as a facilitator, held a public meeting at City Hall regarding the adaptive reuse of Charity Hospital. Numerous people and parties attended, and emotions ran high against the state's failure to retrofit Charity - or even discuss that option. The facilitator was visibly shaken by the raucous experience.
Recently, several consulting parties have learned that they were not given actual notice of two public meetings held on March 16 and March 30 regarding the adaptive reuse of Charity Hospital. Not a single member of the public attended either meeting - and, indeed, it's unclear whether the third meeting was only held because notice wasn't actual run in a timely fashion in the paper...or because not a single person attended the second meeting. The BioDistrict and LSU had people on hand, but they apparently were not considered public attendees by the organizers, which is strange.
Talking to several consulting parties, it seems nobody was even emailed by the state or Jacobs regarding these meetings. The state did tuck at least one notice in the back sections of the Times-Picayune, however. Here's the only one I can find.
This was very clearly an attempt to evade giving consulting parties and the public notice of the public meetings. The state will argue that the fine print newspaper notices were sufficient to meet its obligations of notice, and that it has now fulfilled its public meetings requirements. And perhaps that would or would not fly in a court of law.
But it's downright shady. It's shady as all hell. Mr. Bilyeu with Jacobs Engineering definitely has the emails of the consulting parties that are to be provided with notice per a September 2010 mass email he sent out regarding an adaptive reuse workshop (not a public meeting). From my experience in several Section 106 processes, the federal agency or responsible entity typically emails the consulting parties regarding meetings. Consulting parties have indicated that they have either a position or an interest that goes even beyond that of the public more generally when it comes to participating in the process.
Keep in mind, too, that these March public meetings are coming AFTER a January Jacobs-headed meeting to issue an RFP for Charity - a meeting that consulting parties were not told about.
Here's the requirement in the Programmatic Agreement that governs the Charity adaptive reuse process:
FP&C will endeavor to promote adaptive reuse for those nine
historically significant buildings that neither it nor other state
agencies use. During this process, FP&C will give notice to the
SHPO and to those groups and individuals who participated in this
Section 106 process as Consulting Parties. Additionally, public
meetings and/or forums will be held at no less than 2 points in the
process of evaluating the reuse or transfer of these properties from
State control, to solicit input and comments from the interested
parties.
My overarching question: what are they so afraid of...? Public meetings or forums on adaptive reuse don't even involve binding input. To diverge from past notice practices to avoid attendance and to have zero attendance subsequently result shows an intentional desire by Facilities Planning and Control to keep the public from having a say as mandated in the programmatic agreement.
Now that the BioDistrict has been shopping around its own proposals for reuse of the building, it's all starting to make a bit more sense. Mr. Jim McNamara, head of the BioDistrict, was at both March meetings.
Recently, several consulting parties have learned that they were not given actual notice of two public meetings held on March 16 and March 30 regarding the adaptive reuse of Charity Hospital. Not a single member of the public attended either meeting - and, indeed, it's unclear whether the third meeting was only held because notice wasn't actual run in a timely fashion in the paper...or because not a single person attended the second meeting. The BioDistrict and LSU had people on hand, but they apparently were not considered public attendees by the organizers, which is strange.
Talking to several consulting parties, it seems nobody was even emailed by the state or Jacobs regarding these meetings. The state did tuck at least one notice in the back sections of the Times-Picayune, however. Here's the only one I can find.
This was very clearly an attempt to evade giving consulting parties and the public notice of the public meetings. The state will argue that the fine print newspaper notices were sufficient to meet its obligations of notice, and that it has now fulfilled its public meetings requirements. And perhaps that would or would not fly in a court of law.
But it's downright shady. It's shady as all hell. Mr. Bilyeu with Jacobs Engineering definitely has the emails of the consulting parties that are to be provided with notice per a September 2010 mass email he sent out regarding an adaptive reuse workshop (not a public meeting). From my experience in several Section 106 processes, the federal agency or responsible entity typically emails the consulting parties regarding meetings. Consulting parties have indicated that they have either a position or an interest that goes even beyond that of the public more generally when it comes to participating in the process.
Keep in mind, too, that these March public meetings are coming AFTER a January Jacobs-headed meeting to issue an RFP for Charity - a meeting that consulting parties were not told about.
Here's the requirement in the Programmatic Agreement that governs the Charity adaptive reuse process:
FP&C will endeavor to promote adaptive reuse for those nine
historically significant buildings that neither it nor other state
agencies use. During this process, FP&C will give notice to the
SHPO and to those groups and individuals who participated in this
Section 106 process as Consulting Parties. Additionally, public
meetings and/or forums will be held at no less than 2 points in the
process of evaluating the reuse or transfer of these properties from
State control, to solicit input and comments from the interested
parties.
My overarching question: what are they so afraid of...? Public meetings or forums on adaptive reuse don't even involve binding input. To diverge from past notice practices to avoid attendance and to have zero attendance subsequently result shows an intentional desire by Facilities Planning and Control to keep the public from having a say as mandated in the programmatic agreement.
Now that the BioDistrict has been shopping around its own proposals for reuse of the building, it's all starting to make a bit more sense. Mr. Jim McNamara, head of the BioDistrict, was at both March meetings.
Monday, November 1, 2010
BioDistrict Public Meetings this Week
If you live in the VA or LSU Hospital footprints, you also reside within the much larger footprint of "BioDistrict New Orleans" planned for a 1,500-acre campus in Mid-City and Gert Town.
Several public meetings are scheduled for this later this week:
If you're not familiar with the project, which is overseen by an unelected board, you should attend...if only to see whether your home or business falls within an "opportunity zone" proposed by the project.
Several public meetings are scheduled for this later this week:
If you're not familiar with the project, which is overseen by an unelected board, you should attend...if only to see whether your home or business falls within an "opportunity zone" proposed by the project.
Labels:
BioDistrict,
euphemisms,
GNOBEDD,
Lower Mid-City,
Mid-City,
notice,
opportunity zones,
public input
Wednesday, October 13, 2010
"Reuse and/or Disposition of Charity Hospital"
There's a meeting in the City Council chambers on Monday night - and public comment will be permitted.
Friday, February 12, 2010
The Federal Suit
Here's the rundown on the footprint-related suit in federal court here in New Orleans:
I wasn't able to attend the summary judgment hearing on Tuesday, but I'm interested to see how Judge Fallon ultimately rules on the motions.
A lawsuit filed by the National Trust for Historic Preservation claims that government parties violated the National Environmental Policy Act when they fast-tracked the required pre-construction review to bypass a comprehensive "environmental impact statement." Among other counterarguments, Veterans Affairs and the Federal Emergency Management Agency say they are due the court's deference when considering the methodology used in satisfying the rules that govern all construction projects financed with federal tax money.
I wasn't able to attend the summary judgment hearing on Tuesday, but I'm interested to see how Judge Fallon ultimately rules on the motions.
Monday, January 11, 2010
VA Footprint - Important Public Input Notice
The Preservation Resource Center provides an overview of the public input process that unfolds over the next month regarding the VA medical center site. Public comment is welcome and will determine whether the VA project will have any "significant impact" on Lower Mid-City, which could necessitate additional studies.
Here's the (facebook) link.
Here's the (facebook) link.